Caterpillar Inc.
SYSTEM AND METHOD FOR WORKSITE PROJECT TRACKING

Last updated:

Abstract:

A method includes receiving target data for a paving project corresponding to a work period. The method also includes receiving sensor data from one or more components associated with the paving project, determining a progress value representing progress of the one or more components of the paving project, and determining a threshold progress value for a time period, the time period having a duration that is less than a duration of a work period. The method further includes determining that the progress value is less than the threshold progress value, generating at least one of an alarm or a recommendation, and sending the alarm or the recommendation to an electronic device.

Status:
Application
Type:

Utility

Filling date:

16 Oct 2019

Issue date:

22 Apr 2021