  • Operator:
    Welcome to the Eversource Energy First Quarter Earnings Call. My name is Vanessa, and I will be the operator for your call today. At this time, all participants are in a listen-only mode. Later, we will conduct a question-and-answer session. Please note that this conference is being recorded. I will now turn the call over to Mr. Jeffrey Kotkin, Vice President for Investor Relations. Sir, you may begin.
  • Jeffrey R. Kotkin:
    Thank you, Vanessa. Good morning and thank you for joining us. I'm Jeff Kotkin, Eversource Energy's Vice President for Investor Relations. As you can see on slide 1, some of the statements made during this investor call maybe forward-looking as defined within the meaning of the Safe Harbor provisions of the U.S. Private Securities Litigation Reform Act of 1995. These forward-looking statements are based on management's current expectations and are subject to risk and uncertainty, which may cause the actual results to differ materially from forecasts and projections. Some of these factors are set forth in the news release issued yesterday. Additional information about the various factors that may cause actual results to differ can be found in our annual report on Form 10-K for the year ended December 31, 2016. Additionally, our explanation of how and why we use certain non-GAAP measures is contained within our news release and the slides we posted last night on our website under Presentations & Webcasts, and in our most recent 10-K. Turning to slide 2, speaking today will be Phil Lembo, our Executive Vice President and CFO; and Lee Olivier, our Executive Vice President for Enterprise Energy Strategy and Business Development. Also, joining us today are Werner Schweiger, our Executive Vice President and Chief Operating Officer; Jay Buth, our Vice President and Controller; and John Moreira, our Vice President of Financial Planning and Analysis. Now, I will turn to slide 3 and turn over the call to Phil.
  • Phil Lembo:
    Thank you, Jeff. Today, I'll cover four items
  • Leon J. Olivier:
    Okay. Thanks, Phil. I'll provide you with a brief update on our major investment initiatives and then turn the call back to Jeff for Q&A. So let's start with Northern Pass on slide 7. The New Hampshire Site Evaluation Committee commenced final evidentiary hearings for the project on April 13 after rejecting several motions from the project opponents for a delay. Hearings are now scheduled to run through early August and we have been quite pleased with how they have proceeded thus far. We consider the New Hampshire SEC schedule to be supportive of the Committee's stated objective of issuing a final written order no later than September 30, 2017. Hearings in April focused on two of the key criteria that must be considered. These criteria include whether Northern Pass and Eversource have the technical, financial and managerial capability to construct, operate and maintain the project and whether approval of the project serves the public interest. These are foundational issues in the SEC review process. Our witnesses were very well-prepared and credible in responding to intervening questions, and those panels were completed on schedule. Earlier this week, hearings continued on the more technical aspects of the project and have continued to proceed quite well. Prior to the start of the hearings, the two key permitting agencies, the Department of Environmental Services and Transportation recommended approval of the project by the SEC. Both departments approved their respective permits for the project. We received the Department of Environmental Services recommendations and permits in early March and the report from the Department of Transportation in early April. The recommended conditions from these agencies were reasonable and consistent with our design. In addition, the State Division of Historical Resources, which is not one of the permitting agencies, also continues to review the project and, in its recent status report, concurred that their review of the process is on track. Nothing more is needed from the DHR before the SEC decision is reached. Once the New Hampshire SEC process is complete and assuming the project is approved with reasonable conditions, we expect a U.S. Department of Energy – a presidential permit to be issued by the end of this year. Before that point, probably late in the third quarter, we expect the DOE to release its final Environmental Impact Statement on Northern Pass. The preliminary EIS supporting the issuance of the presidential permit was issued nearly two years ago, and the DOE held a number of public meetings on the draft EIS in late 2015 and early 2016. While we have been advancing the project on the U.S. side of the border, Hydro-Québec has been pursuing siting on the Canadian side. The three-year Canadian process should be completed this summer, so by the end of this year, we expect Northern Pass to be fully permitted in both the United States and Canada. This supports our plan to move into the construction phase in the first quarter of 2018. In addition to the New Hampshire SEC, the New Hampshire Public Utilities Commission has been reviewing several items related to Northern Pass. You may recall that last year, Northern Pass was granted utility status by the PUC conditional upon receiving approval of the project from the SEC. In early April, following a preliminary review, the PUC ruled that it could move ahead with their review of the terms of the NPT proposed lease of Public Service of New Hampshire Transmission rights of way. That decision was also over the objection of project opponents. We expect a PUC decision on the proposed lease terms later this year. In March, the PUC also ruled on a 100-megawatt power purchase agreement signed last year by PSNH and Hydro-Québec. The PUC said that under the current state restructuring law, it did not have authority to approve such a PPA with PSNH. Such a contract is not required for siting or to move ahead with the project. In late March, the New Hampshire Senate overwhelmingly approved and sent to the House of Representatives Senate Bill 128, which would expand the PUC's authority to consider long-term contracts that would lower customer cost and improve grid reliability and fuel diversity. The current legislative session is due to end in late June, so we'll be watching the progress of this bill closely. We and Hydro-Québec will bid the Northern Pass project into the Clean Energy RFP that Massachusetts commenced March 31 for up to 9.45 terawatt hours annually for a period of up to 20 years. Bids are due on July 27 and the schedule indicates that the projects will be selected for negotiations by January 25. Separately, a draft RFP exclusively for offshore wind was filed by Massachusetts utilities with the DPU last week. The schedule calls for the RFP to be final and issued to the market by June 30, 2017. The RFP calls for interested bidders to submit at least one proposal for at least 400 megawatts. The draft also stated that alternative bids for up to 800 megawatts would be considered if bidders can show that a larger project would provide significant net economic benefits to customers. Bidders can also submit an alternative bid for as little as 200 megawatts. The timeline of the draft RFP calls for the selection of the winning bids by the spring of 2018 and the submission of contracts to the DPU by late 2018. Bay State Wind, a 50/50 partnership between Eversource and DONG Energy, will bid into the RFP. Finally, turning to slide 8, (20
  • Jeffrey R. Kotkin:
    Thank you, Lee. And I'm going to turn the call back to Vanessa just to remind you how to enter the Q&A queue.
  • Operator:
    And thank you.
  • Jeffrey R. Kotkin:
    Thank you, Vanessa. Our first question this morning is from Julien Dumoulin-Smith from UBS. Good morning, Julien.
  • Jerimiah Booream:
    Jerimiah Booream. How are you?
  • Jeffrey R. Kotkin:
    Hey, Jerimiah.
  • Jerimiah Booream:
    So just a quick question on the new project that was announced by National Grid, the Granite State Power Link. Do you guys view this as a competitor? And to the extent, you can provide any commentary around how that would impact your thought process on moving forward with your own project?
  • Leon J. Olivier:
    Yes. Jerimiah, this is Lee. No, we don't really look at that as a viable project for the April RFP. Obviously, they would have to go through the entire presidential permitting process. They would have to – which can take many years, as you know. They would have to go through siting in Vermont and New Hampshire in the – they don't have a supplier of energy, they don't have an interconnection into Canada, the Canadian process of three years. So when you look at the April RFP and you look at the preference in the Massachusetts RFP for projects that are in service by the end of December of 2020, we do not believe that is a viable alternative, which is not to say...
  • Jerimiah Booream:
    Okay.
  • Leon J. Olivier:
    ...it couldn't be a project for a future RFP.
  • Jerimiah Booream:
    Yeah. Got it. And then, just on Access Northeast, is there any progress on legislation that's been moving forward or any commentary or update there?
  • Leon J. Olivier:
    Yeah. I just think the general commentary there is we just continue to have those conversations with legislators, we continue to educate them on the alternatives to not building a pipeline from the standpoint of threats to reliability and extreme volatility during the wintertime. And of course, as I mentioned, ISO is working on their no gas pipeline solution, which we believe will cause them to require certain actions to be taken that will not be in the best interests of the region's goals to reduce carbon and it will not be in the best interest of maintaining price stability for our customers.
  • Jerimiah Booream:
    Okay. Thanks very much.
  • Leon J. Olivier:
    Welcome.
  • Jeffrey R. Kotkin:
    Thanks, Jerimiah. Next question is from Mike Weinstein from Credit Suisse. Good morning, Mike. Michael Weinstein - Credit Suisse Securities (USA) LLC Hi. Good morning. Hey, just a follow-up on Jerimiah's questions a little bit. For the Northern Pass project, could you comment on – is there any chance at all that the hearings could be pushed beyond September 30? What's your sense that September 30 is a good hard deadline in terms of their commitment to meeting at the Commission?
  • Leon J. Olivier:
    Yeah. Mike, this is Lee. I would just say that the New Hampshire SEC has been very precise, very comprehensive in how they have run the proceedings to date. They are right on schedule. I think the more testimony that is given and provided by the project, the clearer the project becomes. And we don't see at this point any probability or possibility that this date will be extended. I mean the meetings have been very crisp. The witnesses are very well-prepared and with the ability to answer all of the questions to-date. Michael Weinstein - Credit Suisse Securities (USA) LLC All right. Great. And to what extent is the land-based renewables RFP important for Northern Pass or not important?
  • Leon J. Olivier:
    Well, clearly, it is important from the standpoint that you have Hydro-Québec that wants to sell their energy into the New England marketplace. And if there is the ability to participate inside of an RFP and get a long-term contract at a fixed price, that's an advantage to HQ. So, clearly, there's an advantage there, but in any case, the RFP in and of itself does not determine the longevity of the project and the success of the project, because, in fact, there will be many RFPs, there will be many retirements. As we've said before, we see about 10,000 megawatts of retirements in New England, and Northern Pass will be viable in any of those as a source of clean energy for the region. Michael Weinstein - Credit Suisse Securities (USA) LLC Right. Great. And just one last one for Phil. Hey, on the – I'm sorry if I missed this, but can you just remind us what – as you head into the Massachusetts rate cases for NSTAR and WMECO, what is the earned ROEs at these utilities going into the case? And what are you seeking coming out of it? How important are these rate increases for these utilities?
  • Phil Lembo:
    Yeah, Mike. So, in the request, we're looking for a 10.5% ROE in the case and the total rate increase is about $60 million at NSTAR Electric and about $36 million at Western Mass Electric. So not – certainly, they're increases, but not double-digit types of increases. So we're earning close to those numbers. NSTAR Electric at the end of 2016 was probably a little shy of that number of 10.5% when you do all the calculations for Massachusetts, and Western Mass was closer to 9%, so not at the levels that we were looking for in this case. Michael Weinstein - Credit Suisse Securities (USA) LLC Okay. Thanks a lot, guys.
  • Jeffrey R. Kotkin:
    All right. Thanks, Mike. Next question is from Praful Mehta from Citi. Good morning, Praful.
  • Praful Mehta:
    Morning, guys. Thanks. So just a quick question on Access Northeast, more around what are the risks to timing and if there are delays, just wanted to understand what is the capital allocation strategy. Is it to wait and hold on to the capital to see when you actually can deploy towards Access Northeast? Or is there any share buyback or anything else on the cards if there are meaningful delays around Access Northeast?
  • Phil Lembo:
    Yeah. So this is Phil, Praful. What we've said in our long-term forecast of 5% to 7% that Access Northeast is really a small part of the far end of that forecast. So it's not as if there'd be a significant amount of capital that we're expecting in our plan over the next two to three near-term years, so there really wouldn't be a significant amount of capital to think about redeploying. In terms of share repurchases, we're primarily interested, as we've said, in infrastructure that meet the needs of our customers and the region's energy needs. And really, we're looking for projects that are clean, that improve reliability and that manage to keep customer costs in line. So we don't have a share repurchase program authorized, and our focus would be on the infrastructure development.
  • Praful Mehta:
    Got you. Fair enough. And just quickly, any color on FERC ROE given all this uncertainty on where the ROE finally shows up, and as you laid out, the implications for you guys based on the invested capital you have on the transmission side? How do we think about the timing of how this plays out? How are you guys viewing it internally? You said you're going to review whether using your existing rate is the right one going forward in terms of your forecast. So, I guess, if you can just put out at least the boundaries of how we should think about the potential outcomes here.
  • Phil Lembo:
    Sure. I guess, in the basic part of your – element of your question really I think gets to the point which is the situation is very fluid. The court decision is still recent, and really, the New England transmission owners, as a group, need to decide what the next steps will be. So that probably is a near-term determination because, in June, the transmission owners need to file a proposed regional network service rate. So it's certainly an active topic for discussion right now with the New England transmission owners. So one could say that the last approved ROE by FERC is the 11.14%, so that's the last actual number that's out there. So any other number is as good as any other number if it's not 11.14%. So we're on top of this right now, we're working with the other transmission owners, but I think you should see more from all of us in the near-term.
  • Praful Mehta:
    Got you. Thank you, guys.
  • Phil Lembo:
    Okay.
  • Jeffrey R. Kotkin:
    Thanks, Praful. Next question is from Travis Miller from Morningstar. Good morning, Travis.
  • Travis Miller:
    Good morning. Thank you. I was wondering, real quick, on the gas distribution demand side, you've mentioned the 4.6% increase in the breakout of the numbers. How much of that was core and non-weather-related? And is that tracking along your plan?
  • Phil Lembo:
    Well, as I said, versus normal, it's below. We've had to – the comparison of this year to last year was better, because it was a bit colder this year. But as I said, both 2017 and 2016 were quite a bit below normal, in the neighborhood of 6% to 7% heating degree days being below normal there. So we generally plan to normal, so I would expect that number would have been higher had we had hit normal weather.
  • Travis Miller:
    The 4.6% would have been higher?
  • Phil Lembo:
    Correct. Yeah. It was below normal weather in the first quarter.
  • Travis Miller:
    Okay. Okay. And then, just generally...
  • Phil Lembo:
    Because I said...
  • Travis Miller:
    What's that?
  • Phil Lembo:
    Oh. Go ahead. Go ahead.
  • Travis Miller:
    Yeah. Just generally, when you think about all the regulatory stuffs going on, the rate cases at FERC, the transmission projects with gas or electric would you say are the number one or two most important, most critical outcomes or resolutions that you need for the company overall, and particularly shareholders?
  • Phil Lembo:
    Well, Travis, I think I've always said when you're in a business where 100% of your revenues are determined in a regulatory arena, certainly, positive regulatory outcomes are important across the board. And if there's one company that you can point to as the poster child for getting two positive regulatory outcomes and having constructive relationships, whether they be at the state level or other, it's Eversource. So we feel very good about our abilities there and our ability to work with constructive regulation in the states. So I think they're all important, because we are highly-regulated obviously, but we do an effective job there.
  • Travis Miller:
    Okay. Great. Thanks so much.
  • Jeffrey R. Kotkin:
    Thanks, Travis. Next question is from Caroline Bone from Deutsche Bank. Good morning, Caroline.
  • Caroline V. Bone:
    Hey. Good morning, guys. I just have some follow-up questions on Northern Pass. So last quarter, you guys talked about the need to place an order for certain equipment. I was just wondering if you had any further idea on when that order might be placed?
  • Leon J. Olivier:
    Yeah, Caroline. This is Lee. The schedule that we have right now with the SEC in New Hampshire is really – May is really all about a couple of things. It's all about construction and it's all about the environmental impact, and that ends probably in the beginning of June. And then, at that point in time, we'll have a better sense of the construction practices. We'll have a better sense of any other environmental impact that may cause us to change the equipment orders from our current design. So I think we'll be in a better position then to look at making those orders around that period of time. We continue to have conversations with the vendors, such as ABB, and to understand more about what will be required to do the design and construction or manufacturing, but really, we need to get to the beginning of June to have a better sense of that.
  • Caroline V. Bone:
    All right. That's very helpful, but I guess one just follow-up to that. Does the Massachusetts Clean Energy RFP have any impact on when that order might be placed? Or is it kind of a separate issue?
  • Leon J. Olivier:
    I would conclude that that's really a separate issue. It's really all about understanding what the final design is, because we don't want to go forward, order equipment, kick off engineering in and around it, only to find out the design is different and that becomes a re-do and is an expense that we don't want to incur.
  • Caroline V. Bone:
    Okay. Thanks. And then, just one more minor one. With regards to the final EIS from the DOE, do they want to see the final SEC decision before they put out their final EIS?
  • Leon J. Olivier:
    No, not necessarily. The presidential permit will come after the SEC decision. So you'll have the final EIS, you'll have the SEC outcome, and then, you get the presidential permit, so no, they don't need to see that.
  • Caroline V. Bone:
    All right. Thanks very much.
  • Leon J. Olivier:
    Welcome.
  • Jeffrey R. Kotkin:
    Thanks, Caroline. The next question is from Paul Zimbardo from Citadel. Good morning, Paul.
  • Paul Zimbardo:
    Hi. Good morning. I had a quick clarification question. I'm sorry, I was a little confused. On Mike and Caroline's question. I know the slide says first quarter 2018 construction commencing; would you commence construction before that, I think you said January 25, RFP selection date?
  • Leon J. Olivier:
    I'm sorry. Is the question...?
  • Jeffrey R. Kotkin:
    He's talking about the Mass RFP identifying winners by January 25, 2018 and would the construction schedule in the first quarter of 2018 depend on what happens on January 25? Is that your question, Paul?
  • Paul Zimbardo:
    Yes. Like if it's – if there was any firmer timing in January – or in first quarter 2018?
  • Leon J. Olivier:
    No. I think currently, where we are is, assuming we have a successful outcome of the SEC process, we will start construction in the first quarter of 2018.
  • Paul Zimbardo:
    Okay, great. Thank you very much.
  • Jeffrey R. Kotkin:
    Thank you, Paul. That's the last question that we have for this morning. So we want to thank you very much for joining us and we look forward to seeing you at the upcoming conferences over the course of May. Take care.
  • Operator:
    And thank you, ladies and gentlemen. This concludes today's conference. Thank you for participating. You may now disconnect.